Dialysis Center Construction

Construction began in November 2024 on the new CMH Dialysis Center. Opening is expected in late fall 2025. Facility features include:

  • 16 hemodialysis chairs, each facing the large windows offering scenic views
  • 4 patient rooms for home hemodialysis and peritoneal dialysis education
  • Waiting room
  • Staff support areas
  • Water room with the latest advancements in purification and sanitization, a Dual Reverse Osmosis water treatment system with heat sanitization technology

The CMH Nephrology Clinic, which opened in September 2024 in the Douglas Medical Center, will move into the dialysis center once the building is complete.

Project Details

  • 10,000-square-foot facility
  • Cost: About $9 million
  • Financing: OakStar Bank in Springfield
  • Architect: Pulse Design Group, Kansas City
  • General contractor: JE Dunn, Springfield

Construction Updates

With the Dialysis Center scheduled to open in December 2025, it is showing signs of being close to completion, both inside and out.

  • Exterior brick and stone is up.
  • Parking lot poured and landscaping being placed.
  • Interior spaces with painted walls, flooring and cabinets.

front of the Dialysis Center

poured parking lot outside the dialysis center

large room with counters and large windows

back side of the building with large windows

The steel structure is complete! Exterior metal wall framing and the layout of interior wall framing will begin in April.

building steel frame

Crews started adding the steel frame in March.

steel frame

 dialysis-feb25.webp

Construction progress in January and February included in-ground plumbing and electrical rough-in. Other activities included backfill and rough grade, pressure testing and fine grading at the building pad.

people turning over dirt with shovels

The groundbreaking ceremony was on Nov. 7, 2024, to kick off the construction. Read more in the event news release.